内蒙古电网110kV智能变电站模块化建设通用设计
Analysis on General Design of Modular Construction of 110kV Smart Substation in Inner Mongolia Power Grid

张振,聂建春,张晓妍,白秀梅,邬超慧
ZHANG Zhen,NIE Jianchun,ZHANG Xiaoyan,BAI Xiumei,WU Chaohui

摘要(Abstract):

基于国家电网公司110 kV智能变电站模块化建设通用设计方案,结合蒙西地区环境区域特点及内蒙古电网变电站建设特点、运行习惯,从二次舱的设置、智能终端和合并单元的布置、装配式构筑物和构支架材料的选取等方面明确了内蒙古电网110 kV智能变电站模块化建设通用设计主要原则,并分析了其与国家电网110 kV智能变电站模块化建设通用设计存在的差异,最终形成内蒙古电网110 kV智能变电站模块化建设通用设计方案,为设计人员提供依据和参考。
Based on the general design scheme for modular construction of 110 kV smart substations of the State Grid Corporation of China, and combined with the characteristics of the environment in the western Inner Mongolia region and the construction characteristics and operating habits of the Inner Mongolia power grid substations, this paper clarifies the main design principles of the general design of the modular construction of the 110 kV smart substation in Inner Mongolia power grid from aspects such as the setting of the secondary cabin, the arrangement of the smart terminal and the merging unit, the selection of prefabricated structures and structural support materials. The paper further analyzes the difference between the principles mentioned and the general design of the modular construction of the 110 kV smart substation of the State Grid, and finally forms a general design scheme for the modular construction of the 110 kV smart substation of the Inner Mongolia power grid, which provides a basis and reference for the application of designers.

关键词(KeyWords): 内蒙古电网;智能变电站;模块化建设;设计原则;预制舱;布置方式
Inner Mongolia power grid;smart substation;modular construction;design principles;prefabricated cabins;layout methods

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 张振,聂建春,张晓妍,白秀梅,邬超慧
ZHANG Zhen,NIE Jianchun,ZHANG Xiaoyan,BAI Xiumei,WU Chaohui

参考文献(References):

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享