| 3 | 0 | 24 |
| 下载次数 | 被引频次 | 阅读次数 |
针对内蒙古电网与华北电网交直流混联格局下的工程建设时序问题,确定了内蒙古电网特高压交直流混联的目标网架结构,并构建了相应的数据模型。基于该模型提出多种特高压交直流建设时序方案。通过时域仿真对现状网架、目标网架及过渡期网架的安全稳定性进行了校核。针对过渡期部分站点短路电流超标以及直流外送通道发生严重故障后的切机问题,提出了相应的控制措施。并从潮流分布、短路电流和稳定性三个方面对各建设方案进行了对比分析,最后基于层次分析法围绕输电能力、潮流转移、短路电流、暂态稳定、动态稳定五个指标构建综合评价体系,通过权重分配、指标量化、得分计算实现方案最优排序,确定了对内蒙古电网最为有利的特高压交直流建设方案。
Abstract:Focusing on the construction sequence issues of power grid projects under the AC/DC hybrid interconnection pattern between the Western Inner Mongolia Power Grid and the North China Power Grid, this paper firstly determines the target grid structure of the UHV AC/DC hybrid interconnection system for the Inner Mongolia Power Grid and establishes a corresponding data model. Based on this model, multiple construction sequence schemes for UHV AC/DC systems are proposed. The safety and stability of the existing grid, target grid, and transitional grid are validated through time-domain simulation. For issues such as short-circuit current exceeding limits at certain substations and generator tripping following severe faults in the DC transmission channels during the transitional period, corresponding control measures are proposed. And a comparative analysis is conducted on various construction schemes from three aspects: power flow distribution, short- circuit current, and stability. Finally, based on the analytic hierarchy process(AHP), a comprehensive evaluation system is constructed around five indicators: transmission capacity, power flow transfer, short-circuit current, transient stability, and dynamic stability. Through weight assignment, index quantification, and score calculation, the optimal ranking of the schemes is achieved, and the most favorable UHV AC/DC construction scheme for the Inner Mongolia Power Grid is determined.
[1] 戚凌铭,刘志军,刘子维,等.基于延时补偿的智能变电站保护装置时序重建方法研究[J].变压器,2026,63(6):25-29. Qi Lingming, Liu Zhijun, Liu Ziwei, et al. Research on the Time Sequence Reconstruction Method of Smart Substation Protection Devices Based on Delay Compensation[J]. Transformer, 2026, 63(6): 25-29.
[2] 武鹏,程浩忠,邢洁,等.基于可信性理论的输电网规划[J].电力系统自动化,2009,33(12):22-26. Wu Peng, Cheng Haozhong, Xing Jie, et al. Transmission Network Planning Based on Credibility Theory[J]. Automation of Electric Power Systems, 2009, 33(12): 22-26.
[3] Wu P, Cheng H Z, Xing J. The interval minimum load cutting problem in the process of transmission network expansion planning considering uncertainty in demand[J]. IEEE Transactions on Power Systems, 2008, 23(3): 1497-1506.
[4] Li Y H, Wang J X, Ding T. Clustering -Based Chance -Constrained transmission expansion planning using an improved benders decomposition algorithm[J]. IET Generation, Transmission & Distribution, 2018, 12(4): 935-946.
[5] 张衡,程浩忠,曾平良,等.基于随机优化理论的输电网规划研究综述[J].电网技术,2017,41(10):3121-3129. Zhang Heng, Cheng Haozhong, Zeng Pingliang, et al. Review of Transmission Network Planning Based on Stochastic Optimization Theory[J]. Power System Technology, 2017, 41(10): 3121-3129.
[6] 刘盾盾,程浩忠,刘佳,等.输电网鲁棒规划研究综述与展望[J].电网技术,2019,43(1):135-143. Liu Dundun, Cheng Haozhong, Liu Jia, et al. Review and Prospect of Robust Transmission Network Planning Research[J]. Power System Technology, 2019, 43(1): 135-143.
[7] 金坚,陈成,冯雷,等.面向输电线路建设规划的三维可视化交互系统研究[J].东北电力技术,2026,47(2):1-5. Jin Jian, Chen Cheng, Feng Lei, et al. Research on 3D Visualization Interactive System for Transmission Line Construction Planning[J]. Northeast Electric Power Technology, 2026, 47(2): 1-5.
[8] Li J, Ye L, Zeng Y, et al. A scenario-based robust transmission network expansion planning method for consideration of wind power uncertainties[J]. CSEE Journal of Power and Energy Systems, 2016, 2(1): 11-18.
[9] 宋新甫,戴拥民,赵志强,等.全球能源互联电网发展的规划技术框架及研究方向[J].电工技术,2018(9):7-10. Song Xinfu, Dai Yongmin, Zhao Zhiqiang, et al. Planning Technology Framework and Research Directions for the Development of Global Energy Interconnection Grid[J]. Electric Engineering, 2018(9): 7-10.
[10] 赵良,易海琼,吴耀武.特高压交直流建设时序优化评估指标体系[J].电力建设,2016,37(1):56-63. Zhao Liang, Yi Haiqiong, Wu Yaowu. Evaluation Index System for Construction Sequence Optimization of UHV AC/DC Projects [J]. Electric Power Construction, 2016, 37(1): 56-63.
[11] 资慧,王银顺,侯益灵.湖南特高压交直流输电建设时序问题研究[J].湖南电力,2014,34(3):21-24. Zi Hui, Wang Yinshun, Hou Yiling. Research on Construction Sequence of UHV AC/DC Transmission in Hunan Power Grid[J]. Hunan Electric Power, 2014, 34(3): 21-24.
[12] 吕盼,李晓珺,张志强,等.天山西段750 kV环网加强工程建设时序研究[J].电气应用,2017,36(6):38-42. Lyu Pan, Li Xiaojun, Zhang Zhiqiang, et al. Research on Construction Sequence of 750 kV Ring Network Reinforcement Project in Western Tianshan[J]. Electrotechnical Application, 2017, 36(6): 38-42.
[13] 李隽,高艺,宋福龙.电网规划风险评估工程综合应用研究[J].电力建设,2014,35(12):14-18. Li Jun, Gao Yi, Song Fulong. Comprehensive Application Research on Risk Assessment of Power Grid Planning Projects [J]. Electric Power Construction, 2014, 35(12): 14-18.
[14] 何裕强,晁凯云,商小峰,等.基于风险指标的特高压直流受端系统预防控制策略[J].东北电力技术,2025,46(6):5-9. He yuqiang, Chao Kaiyun, Shang Xiaofeng, et al. Preventive Control Strategy for Ultra-High Voltage DC Receiving System Based on Risk Indicators[J]. Northeast Electric Power Technology, 2025, 46(6): 5-9.
[15] 袁越,吴博文,李振杰,等.基于多场景概率的含大型风电场的输电网柔性规划[J].电力自动化设备,2009,29(10):8-12. Yuan Yue, Wu Bowen, Li Zhenjie, et al. Flexible Transmission Network Planning with Large-Scale Wind Farms Based on Multi -Scenario Probability[J]. Electric Power Automation Equipment, 2009, 29(10): 8-12.
基本信息:
DOI:10.19929/j.cnki.nmgdljs.2026.0043
引用信息:
[1]郭建华, 慕腾, 刘石川,等.特高压交直流输电工程建设时序研究[J],2026,44(4):52-59.DOI:10.19929/j.cnki.nmgdljs.2026.0043.
基金信息:
国家重点研发计划项目“大规模可再生能源基地特高压多端直流输电外送关键技术”(2023YFB2405900)